Power Systems Training Institute, Bangalore

Power Systems Training Institute (PSTI), Bangalore


Introduction
Training Schedule (April, 2000 - March, 2001)
Training Schedule (April, 2001 - September, 2001)
Course Outline
Training Methodologies
Laboratories
Sponsoring Organisations
Address/ Phone & Fax numbers/ e-mail


I. Introduction

The Central Electricity Authority (CEA), an attached office of Ministry of Power, Government of India established the Power Systems Training Institute at Bangalore in 1972 for providing specialised training in the field of Power Systems mainly to the engineers from Power Utilities.

The Institute is headed by a Chief Engineer.The Institute is located in its own campus and hostel facilities with boarding arrangements are available to the trainee officers.

Specialised laboratories,a well equipped library and a lecture hall complete with modern teaching aids have been set up at the Institute campus for meeting the training requirements. For the engineers attending training programmes in the various disciplines, facilities are provided in the Power Loading Simulator laboratory, Communication laboratory, Relay laboratory and Computer laboratory.

The Institute has a state-of-the-art digital computer based Despatcher Training Simulator. Power system behaviour under different operating conditions can be studied in the simulator.

The faculty for the training programmes comprises in-house faculty as well as experts drawn from I.I.Sc., CPRI, CDAC, DoT, ITI, Utilities and manufacturers.

Training programmes are offered in ten different disciplines in the field of Power Systems and the duration of the course varies from one to four weeks depending upon the programme. In 1983, the Institute had also organised and conducted a special training programme for the benefit of power system managers from ten countries in the ESCAP Region. In addition to these, the Institute is also conducting special courses on HRD programme.



II. Training Schedule

Year: 2000-2001

Sl. No

Name of the course

Period

1 Object Oriented Progrmming in C++ 3rd --- 14th April, 2000
2 Power System Studies 24th April --- 12th May, 2000
3 Operation & Maintenance of Transmission Lines and Sub-Stations 22nd May --- 9th June, 2000
4 Power System Operation & Control 12th, June --- 7th July, 2000
5 Office Automation using PCs (for CEA staff) 26th --- 30th June, 2000
6 HRD Programme for Engineers 17th --- 21st July, 2000
7 Power & Telecommunication Co-ordination 31st July --- 11th August, 2000
8 Power System Protection 21st August --- 15th September, 2000
9 Computer Basics for Engineers 18th --- 30th September, 2000
10 High Voltage Testing of Power System Equipment 9 - 20, October 2000
11 Communications in Power Systems 6 - 24, November 2000
12 HRD Programme for Engineers 27, November - 1, December 2000
13 Object Oriented Programming in C++ 4 - 15, December 2000
14 EHV Sub-station Engineering 18-22, December 2000
15 Despatcher Training Simulator 22, January - 9, February 2001
16 Computerised Load Despatching System 12 - 23, February 2001
17 Advanced Power System Protection 12 - 16 March, 2001

Year: 2001-2002

Sl. No

Name of the course

Period

1 O & M of Transmission Lines and Sub-stations 9 - 20 April, 2001
2 Computer Basics for Engineers 14 - 25 May, 2001
3 Power System Studies 11 - 22 June, 2001
4 Power System Operation and Control 2 - 27 July, 2001
5 HRD Programme for Engineers 6 - 10 August, 2001
6 Power and Telecom Co-ordination 3 - 14 September, 2001

III. Course Syllabus Outline

Power System Operation and Control

Power System Protection

Advanced Power System Protection

O & M of Transmission Lines and Substations

High Voltage Testing of Power System Equipment

Despatcher Training Simulator

Computerised Load Despatching System

Communications in Power Systems

Power and Telecommunication Co-Ordination

Power System Studies

HRD Programme for Engineers

Computer Basics for Engineers

Computer Programming Basics for Engineers

Object Oriented Programming in C++

Office Automation using PCs (for CEA staff)


IV. Training Methodologies


V. Laboratories

i) Despatcher Training Simulator Laboratory

   
The DTS laboratory is commissioned in February '90 with the assistance of UNDP.  
This is a digital simulator in power simulating power system network.  
Presently a representative system of Northern Regional Network is simulated.  
It has all types of generation like hydro, thermal, nuclear, gas and pumped storage
etc and transmission schemes covering 220, 400kV and the generation voltages.  
Also most of the transmission equipment like transformers, transmission lines,
capacitor banks bus/line reactors, SVSc, CBs, Isolators etc. Are represented.

The realtime simulation is carried and for normal and emergency conditions of the 
network with initial conditions.  The behaviour of various elements for different 
loading conditions can be studied in the simulator.  Time tagged or manual events 
can be introduced into the simulator when the simulator is going on.  Protection 
schemes cold be implemented with the help of voltage relays, frequency relays, 
rate of change of fr. Relays, over current relays etc.  The actual system occurances 
can be simulated and saved as save cases.  Hence it is a comprehensive training
tool for training of power system and load despatch operators.

This lab is only one of its kind in the country.

ii) Power Loading Simulator Laboratory

Primarily designed:
· To train engineers in the techniques of economically controlling the system frequency 
  of large power networks 
· To study alternative operating procedures
· To investigate the range of characteristics and responses associated with power 
  generation
Parts of the Simulator:
a) Main Simulator unit  - simulates an area of Load and Generation with 
  system variables displayed in analogue form.
· six generators (steam, hydro, gas, base generation)  including a  pumped storage scheme
· load: by pre-recorded programme; available on tape
· additional grid network (for practising export and import)
b) Load disconnection unit 
c) Tape recorder   - providing load curve to the system
d) Chart Recorder - taking hard copy output of  system variables

The simulator is 4 times faster than real-time. Three  hour load curve is simulated in 
45 minutes.

Operation:
Trainee engineers are given a load curve and characteristics of  the system units. 
They prepare a load schedule in a response sheet such a way that:
* The frequency is maintained at 50 Hz
* The system units are operated economically
* Import/export commitments are met

System generation and load at the start of the simulation time is set. 
The simulator is transferred to programme mode. Tape drive feeds the load curve to 
the system. Trainees carry out the instructions as per the response sheet. 
Frequency is plotted. At the end of the simulation, total cost for the duration of 
the simulation is noted and compared with the standard cost.

iii) Computer Laboratory

The Computer laboroatory is equipped with the following:
Hardware
Pentium Celeron     - 4 nos.
Pentium II machines - 3 nos.
Pentium MMX        - 1 no.
Pentium             - 3 nos.
486 		    - 1 no.
386		    - 3 nos.

Plotters and Printers

Software
Operating systems:   DOS, Windows 3.1, Windows 95, Windows NT Server, UNIX SVR 4.2, Linux
Languages:	     FORTRAN-77, C, C++, PASCAL, Assembler, MS Visual Studio
Application package: MSOFFICE, WORDSTAR, DBASE, AutoCAD, Oracle Server

iv) Powe Line Carrier Communication Laboratory

· PLCC lab is being used for imparting training on Installation testing and 
commissioning of PLCC equipment. 

· It has been provided with latest programmable type PLCC equipment wherein the 
frequency of transmission & Reception between two sub-stations can be changed at 
site by changing the jumper positions in the equipment. Selective level meter and 
level oscillator are being used for generating and measuring dB level of signals. 

· The PLCC protection equipment have also been installed to impart training on
 mechanism of single and double circuit protection by transmission of appropriate signals.

· The PLCC lab. also contains Digital Exchange that can be operated in both PLCC 
mode and P& T mode.

One Remote Terminal Unit(RTU) and two PCs are being used for training on SCADA systems.

v) Relay Simulator Laboratory

The Relay Simulator  Laboratory is housing a set of four panels with indications 
for the type of fault and the status of circuit breaker and isolator.Each of the indicators 
on the panel and the isolator, breakers conditioning can be actuated through the control panel 
switches.
 
Hence the directional relays can be simulated through actuating a set of indications, 
Isolators,  and Circuit Breakers. Based on the indications the trainee will identify 
the type and location of fault on the one line diagram. 

vi) Relay Testing Laboratory

The relay testing lab of PSTI is equipped with English electric make distance relay panel
and the overcurrent relay panel along with associated testing kits.  These relay panels are 
installed about 15 years ago.  They are in perfect working condition for testing the 
directional distance relays and the overcurrent relays.

The lab is also equipped with M/s ABB make non switched static protective relays panel with 
distance differential fuse failure, over-currant and restricted earth fault relays.  
The above relays can be tested with the associated testing kit.	This provides recorder can
fault locator is available in the laboratories supplied by M/s.C&D Instruments (India) Ltd. 
This instrument in association with the distance relays available in the laboratory cna be 
used to demonstrate various types of faults, distance to fault etc.

The Relay Testing Laboratory is associated with the following Relay Testing Equipment.
a. M/S English Electric Make  Electro  Mechanical Type Distance Relays for Single Phase to
   ground and phase to phase  fault conditions  of type MM3V.

b. M/S English Electric Make portable test equipment of Type ZFB for testing distance relays.
   The above equipment are integrated  to test the directional distance relays under single phase 
   to ground  fault and phase to phase fault conditions.

c. M/S English Electric Make Overcurrent Relays' panel with instantaneous and IDMT 
   characteristic relays.

d. M/S English Electric Make portable  Test Equipment of Type CFB for testing overcurrent relays.
   The above equipment are integrated to test the instantaneous  and IDMT characteristics 
   of over current relays  

e. M/S ABB Make  Non-switched static protective relay cubical with the following relays:-
   Distance Protection Relays  of type RAZFE
   Differential Protection Relays of type RADSB
   Over Current Protection Relays of type RXIDF
   Restricted Earth Fault Protection Relays of type RADHD

f. M/S ABB Make Portable Relay Test Set  of  Type TURH to test the  non switched static  relays.
   The above equipment are integrated to test the static distance relays, differential relays, 
   restricted earth fault relays and over current relays.

g. M/S English Electric Make Instantaneous and definite  time Digital Frequency Relay of Type MFVUM
   This equipment is used to test the under frequency  relay characteristics.

h. M/S CSD Make Disturbance Recorder-cum-Fault Locator   of Type IMS8.
   This equipment is used in association with M/s English Electric make relay cubical and ZFB Test
   Set for disturbance recording and fault location.

VI. Sponsoring Organizations

------State Electrcity Boards

  • Andhra Pradesh State Electricity Board
  • Assam State Electricity Board
  • Bihar State Electricity Board
  • Haryana State Electricity Board
  • Himachal Pradesh State Electricity Board
  • Karnataka Electricity Board
  • Kerala State Electricity Board
  • Madhya Pradesh Electricity Board
  • Maharashtra State Electricity Board
  • Meghalaya State Electricity Board
  • Orissa State Electricity Board
  • Punjab State Electricity Board
  • Rajasthan State Electricity Board
  • Tamil Nadu Electricity Board
  • Uttar Pradesh State Electricity Board
  • West Bengal State Electricity Board
  • Electricity Department of Andaman & Nicobar
  • Government of Arunachal Pradesh
  • Government of Goa
  • Government of Jammu & Kashmir
  • Government of Manipur
  • Government of Mizoram
  • Government of Nagaland
  • Government of Pondicherry
  • Government of Sikkim
  • Government of Tripura

    ------Central Govt. Departments

  • Central Electricity Authority
  • Central Power Research Institute
  • Department of Telecommunication
  • Ministry of Railways
  • ------Central Electricity Boards:

  • North Eastern Regional Electricity Board
  • Northern Regional Electricity Board
  • Southern Regional Electricity Board
  • Western Regional Electricity Board
  • Eastern Regional Electricity Board

    ------Companies:

  • Ahmedabad Electric Company Limited
  • Calcutta Electric Supply Company Limited
  • Tata Electric Company Limited
  • Delhi Electricity Supply Undertaking
  • Bhakra Beas Management Board

    ------Corporations:

  • National Hydro Power Corporation
  • National Thermal Power Corporation
  • Neyveli Lignite Corporation
  • Nuclear Power Corporation
  • Power Grid Corporation of India Limited
  • Karnataka Power Corporation Limited
  • Gujarat Power Corporation
  • Damodar Valley Corporation

  • Address:
    Power Systems Training Institute
    P.B. No. 8201, Subramanyapura Road
    Banasankari II Stage
    Bangalore - 560 070

    Phone & Fax:
    S. K. Mohanram, Chief Engineer i/c.........Ph: 080-6661758
    A. Magudapathi, Director.......................Ph: 080-6664255
    Training Division.....................................Ph: 080-6660549
    P&A Division..........................................Ph: 080-6661587
    Fax:.........................................................Fx: 080-6661758

    e-mail: bngpsti@kar.nic.in

    Any feedback or comments shall be sent to bngpsti@kar.nic.in